Press Run Time will now display on Departments using the Press view, and Bindery times will display on Departments using the Bindery view.


Press

Press times will be the same times you see at Order Item level.  The time is calculated by: (Press Sheets divided by Impressions per hour) plus Setup Time.

The total Press time will display in the upper right corner of the screen.  The total time will be calculated off the Order Items showing, so if filter has been selected on the screen, the time will only be calculated off the displayed results.



Bindery

Bindery times will display for any Department Item that has a value in the Pieces per Hour.  The time is calculated by: (Department Item Quantity divide by Pieces per Hour) plus Setup Time.

The total Bindery time will display in the upper right corner of the screen.