Proof Status can be manually changed after the file has been uploaded to DocketManager.


To Manually Change the Proof Status


Adding a Proof Status

Step      Action

  1.         From the Order Item view page, select the {Graphics} tab.

  2.         Select the pencil icon to open the Graphics edit mode. 


  3.         Select a status from the {Proof Status} drop-down menu.


              i.e. If it is the first proof going to the Customer, select {Awaiting Approval}. If it were a Customer

              supplied PDF, select {Approved}, and no other steps would apply.

   4.        Select {Save} from the top-right corner of the Graphics tab. A pop-up window will confirm graphics 

              details saved.

   5.        Select X to close the pop-up window.

   

              Note: Once the status has been added/updated, the Proof Status and Update Date will appear on the                     right-hand side.